John works as a project manager of the NHQ Project. He has created the project network diagram as shown in the figure:

Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity E is delayed by two days?
A. Zero
B. One
C. Four
D. Five
Harry works as the project manager for his organization. He is creating the activity list and would like to tag those activities that are comprised of apportioned effort. Which of the following is the best example of apportioned effort?
A. Adding features to the project's product that is not included in the project scope.
B. Managing the day-to-day events of a project.
C. Creating software as defined in the project scope.
D. Completing project activities as start-to-start events.
Vicky is the project sponsor of Robert's project. She has requested several changes for the project scope and these changes have, of course, been approved. Robert needs to incorporate the project scope changes into the activity list. Where else should Robert reflect these project changes?
A. Project final report
B. Scope baseline
C. Quality control mechanism
D. Cost baseline
You are the project manager for your organization. You are working with your project team to define the project network diagram. Several of the activities in the project schedule appear to have external constraints. Who among the following determines which dependencies are external to the project?
A. Project team
B. Project sponsor
C. Project manager
D. Project management team
Sam works as a project manager for BlueWell Inc. Which of the following processes will he use for selecting a scheduling method, scheduling tool, incorporating project specific data within that scheduling tool to develop a project specific schedule model, and generating project schedule?
A. Constructability Analysis process
B. Schedule Maintenance process
C. Schedule Development process
D. Perform Integrated Change Control process
You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are upposed to be at your second milestone, which accounts for half of the project completion. There have been some errors in the project, which has caused you to spend $2,073,654. Based on the estimate at completion, what is this project's to-complete performance index?
A. -$108,120
B. 1.02
C. $4,608,120
D. 0.98
You are the project manager for your organization. You are discussing an upcoming project with management and they would like you to begin decomposing the project work packages into activities as soon as possible. You have explained to the management that you would like to involve your roject team before the decomposition of the work packages begins. Why would you want your project team to involve in this activity?
A. To understand the exact type of work the project team will be completing
B. To help the activity go faster
C. To get better and more accurate results through the decomposition
D. To create assignments for the project team as the activities are discussed
You are the project manager of the NHL Project for your organization. You are working with your project team to create the schedule baseline for this project. According to you, which of the following statements describes how the schedule baseline is created?
A. It is derived from the constraints of the project.
B. It is assigned to the project by management.
C. It is created by the stakeholders.
D. It is developed from the schedule network analysis.
Which of the following are the outputs to the Determine Budget process? Each correct answer represents a complete solution. Choose all that apply.
A. Project document updates
B. Scope baseline
C. Cost performance baseline
D. Project funding requirements
Which of the following is NOT an output of the control schedule process?
A. Organizational process assets
B. Change requests
C. Project termination request
D. Project document updates