Pass4itsure > PMI > PMI Certification > PMI-SP > PMI-SP Online Practice Questions and Answers

PMI-SP Online Practice Questions and Answers

Questions 4

Mark is the project manager of the GHQ Project. He is happily reporting that his project has a schedule performance index of 2.12. Management, however, does not think this is good news. What is the most likely reason why management does not like an SPI of 2.12?

A. It is not good news because a larger number means the schedule duration estimates were likely to be wrong to begin with.

B. They likely do not understand the SPI formula.

C. It is not good news, as the number should be closer to 100 than 0.

D. It is good news, but Mark may have large cost variances to achieve this value.

Buy Now
Questions 5

Jim is the project manager for his project. He and his project team are creating their duration estimates for the work packages in the WBS. For each activity, Jim is adding a few hours to the duration estimate in case something goes wrong during the completion of the work activity. Sarah, the project sponsor, does not approve of this and warns Jim of Parkinson's Law. What is Parkinson's Law?

A. People will behave based on what their behavior brings them.

B. As employees do repetitive tasks, duration should decrease.

C. Work expands to fill the amount of time allotted to it.

D. An exponential increase labor does not correlate to an exponential decrease in duration.

Buy Now
Questions 6

Laura is the project manager for her organization and management has requested her to create a report on her project's performance. Laura needs to analyze her current project performance and then compare it against what, in order to create a performance report?

A. Cost variances and Cost Performance Index

B. Scope baseline

C. Performance measurement baseline

D. Schedule variances, planned value, and the Schedule Performance Index

Buy Now
Questions 7

You are the project manager of the NHQ project. You are working with your project team to create the project schedule and the project network diagram. In order to start the sequencing of the project activities, you will need a document to identify the result of project phases, key project deliverables, and significant, timeless events in the project. Which of the following documents will you need to help sequence the project work?

A. Activity attributes

B. Activity list

C. Project scope statement

D. Milestone list

Buy Now
Questions 8

Amy works as a project manager for BlueWell Inc. She is working on the SDI project, which has a BAC of $2,816,000. She is currently 20 percent complete with this project, though she should be 25 percent complete with the project work. The project has consumed $495,000 of the project budget to date. Management has asked her the project's Estimate To Complete (ETC) based on the current project performance. What is the ETC for this project?

A. $1,312,504

B. $1,979,952

C. $1,541,544

D. $2,474,952

Buy Now
Questions 9

Gary is the project manager of the GHY project. He has elected to use a previous, but similar, project to guide him and the project team through the estimate activity duration process. The previous project schedule could best described as which one of the following?

A. Organizational process asset

B. Lessons learned documentation

C. Process input

D. Predecessor project

Buy Now
Questions 10

Tom is the project manager for the ABC Construction Company. As part of the project scheduling for the construction of a new office building, he has allotted time for the inspectors of the building structure, as well as electrical, plumbing, and safety into the project's schedule. These inspectors can be considered what type of dependency in the project?

A. Mandatory dependencies

B. Required dependencies

C. Discretionary dependencies

D. External dependencies

Buy Now
Questions 11

Which of the following techniques is used in businesses to determine the effect different costs or investments have on profit and other financial indicators?

A. Schedule analysis

B. Resource leveling

C. What-if scenario analysis

D. Root cause analysis

Buy Now
Questions 12

John is a scheduler in ABC Company. He has to plan an activity for the schedule models. Which of the following activities will he use to make the schedule models? . Each correct answer represents a complete solution. Choose all that apply.

A. Hammocks

B. Critical path scheduling

C. Flags

D. Tasks

Buy Now
Questions 13

You are the project manager of the NNN Project. Stakeholders in the two-year project have requested to send status reports to them via email every week. You have agreed and are sending the reports on each Thursday. After six months of the project, the stakeholders are pleased with the project progress and they would like you to reduce the status reports to every two weeks. What process will examine the change to this project process and implement it in the project?

A. Project change control process

B. Perform integrated change control process

C. Configuration management

D. Communications management

Buy Now
Exam Code: PMI-SP
Exam Name: PMI Scheduling Professional
Last Update: Apr 24, 2024
Questions: 323
10%OFF Coupon Code: SAVE10

PDF (Q&A)

$45.99

VCE

$49.99

PDF + VCE

$59.99