Questions 4

A municipal agency manages a city's water and wastewater infrastructure. A regulation requires the replacement of sewer lines throughout the city at a cost of US$2 billion over 30 years

The city has been managing this program with various program teams, and has a project controls office In place to track protects separate from the program management team A program manager is hired to standardize all deliverables from component projects under the program.

What should the program manager do next?

A. Develop a program management framework

B. Create a program performance analysis report

C. Generate a program charter

D. Establish a program management office (PMO)

Buy Now
Questions 5

Which two of the following items should be considered for inclusion in a comprehensive working outline of a SoW? (Select two options.)

A. Schedule

B. Contract administration

C. Legal matters

D. Technical considerations

E. Financial matters

Buy Now
Questions 6

In which phase of the protect design would an ICT distribution designer be expected to prepare preliminary cost estimates?

A. CD

B. SD

C. PD

D. DD

Buy Now
Questions 7

The program manager of a multinational program must reconcile data including subject matter experts* labor hour estimates and other direct resource hour estimates. In addition the program manager must prepare the cash flow analysis

Which of the following should be considered to get a baseline budget?

A. Currency exchange rates

B. Component cost estimates

C. Baseline schedule

D. Program payment schedules

Buy Now
Questions 8

What is the MINIMUM clearance needed between the front of the telephone booth and any wall or fixture for most installations?

A. 300 mm (12 in)

B. 450 mm (18 in)

C. 610 mm (24 in)

D. 914 mm (36 in)

E. 2.4 m (8 ft)

Buy Now
Questions 9

A program manager notices that one project manager tends to withdraw during important team discussions to avoid conflict. What technique could the program manager use to gam more input from this project manager?

A. Institute an incentive program to create competition among the team members.

B. Make the project manager share an office with a more assertive team member

C. Solicit ideas from each team member individually, giving each person a chance to express their opinions

D. Create an online message board so team members can see and respond to everyone's ideas

Buy Now
Questions 10

During the design phase, drawings for ICT communications spaces should be reviewed for Standards compliance and

A. cost projections.

B. OSHA specifications

C. client requirements

D. equipment availability

Buy Now
Questions 11

What would be the pair color of pins 3 and 6 of a T568B 8 pin modular jack?

A. Green

B. Brown

C. Orange

D. Blue

Buy Now
Questions 12

OSP cables routed inside a building are influenced by fire codes.

A. True

B. False

Buy Now
Questions 13

Class C suspension strands are used for corrosive environments such as in industrial or coastal area.

A. False

B. True

Buy Now
Exam Code: RCDD
Exam Name: BICSI Registered Communications Distribution Designer - RCDD
Last Update: May 05, 2025
Questions: 427
10%OFF Coupon Code: SAVE10

PDF (Q&A)

$49.99

VCE

$55.99

PDF + VCE

$65.99