Questions 4

Which stakeholder interest does the senior supplier represent?

A. Those who will use the project outputs to deliver forecasted benefits

B. Those providing administrative services and advice during the project

C. Those ensuring the project delivers value for money during the project

D. Those providing maintenance and support services after project closure

Buy Now
Questions 5

According to the `defined roles and responsibilities' principle, how many categories of stakeholder interest need to be represented in the project management team?

A. One

B. Two

C. Three

D. Six

Buy Now
Questions 6

What is the purpose of the project brief?

A. To trigger the `starting up a project' process

B. To provide the basis for the `initiating a project' process

C. To plan the benefits reviews required during the project

D. To provide a baseline to measure the project against

Buy Now
Questions 7

Which product summarizes progress and is used to decide whether to amend the project scope or stop the project?

A. Checkpoint Report

B. End Stage Report

C. End Project Report

D. Product Status Account

Buy Now
Questions 8

Which is shown in a product breakdown structure?

A. Management stages, major products and control points

B. In which order the products should be created

C. The major products that are to be developed in a plan

D. What resources are required to develop the products

Buy Now
Questions 9

Which product describes the roles and responsibilities for achieving the effective management of anticipated threats and opportunities in a project?

A. Quality Management Strategy

B. Risk Management Strategy

C. Communication Management Strategy

D. Configuration Management Strategy

Buy Now
Questions 10

Which theme assesses and controls uncertainty within a project?

A. Progress

B. Risk

C. Change

D. Plans

Buy Now
Questions 11

Which defines the sequence in which the products of a plan should be developed?

A. Product Description

B. Product breakdown structure

C. Project Product Description

D. Product flow diagram

Buy Now
Questions 12

Which of the following is a specific quality review team role?

A. User

B. Approver

C. Reviewer

D. Project Support

Buy Now
Questions 13

Which product would hold details of each product's current version and any important relationships between them?

A. Product Description

B. Highlight Report

C. Configuration Item Record

D. Work Package

Buy Now