Pass4itsure > CompTIA > CompTIA Certifications > PK0-005 > PK0-005 Online Practice Questions and Answers

PK0-005 Online Practice Questions and Answers

Questions 4

During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update next?

A. Schedule

B. Status report

C. Issue log

D. Task board

Buy Now
Questions 5

Given the following network diagram:

Which of the following is the critical path?

A. A-C-G-K-M

B. A-B-D-l-L-M

C. A-B-E-J-L-M

D. A-B-F-L-M

Buy Now
Questions 6

Project stakeholders have asked the team to use Scrum to run a software implementation project. Which of the following is most likely to take place during a Scrum ceremony?

A. Reviewing project blockers

B. Defining roles and responsibilities

C. Establishing a project schedule

D. Determining a project budget

Buy Now
Questions 7

A PM is working on the schedule for a project that has technical tasks and requires a SME's knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the best tool to track this data?

A. Gantt chart

B. Project organization chart

C. Program Evaluation Review Technique chart

D. Milestone chart

Buy Now
Questions 8

During the execution phase of a project, team members have been constantly disagreeing about the tasks they have been assigned. Which of the following is most likely the reason they are disagreeing?

A. Some work packages are missing from the WBS.

B. Information is missing from the RACI matrix.

C. New knowledge bases were introduced.

D. Team touch points are missing.

Buy Now
Questions 9

A project team member recalls a specific chat with another member that contained key information related to a previous project, which no one else on the project team is aware of. Which of the following best describes what was needed to address this concern?

A. Integrity

B. Security

C. Archival

D. Lessons learned

Buy Now
Questions 10

A project manager is using an agile methodology to lead the implementation of several features that should be developed concurrently. Which of the following items should the project manager view as a concern?

A. Each feature will have a different owner.

B. The majority of the team can only meet on a weekly basis.

C. The stakeholders have provided a specific deadline to meet.

D. Each feature has a specific budget allocation.

Buy Now
Questions 11

A project manager has been scheduling and facilitating project meetings, scribing the minutes, distributing the minutes, and sending agendas prior to upcoming meetings. However, the project manager is frustrated because action items are not being completed. Which of the following should the project manager do to alleviate these concerns?

A. Use a software tool during the meeting that can create a transcript of what is discussed.

B. Have a standing agenda that is vague enough so that it can be used again.

C. Delegate the roles and responsibilities to improve meeting management.

D. Reprimand project team members for not completing assigned action items.

Buy Now
Questions 12

A project manager has been informed that the delivery of required IT equipment will be delayed. Which of the following is the FIRST step the project manager should take?

A. Make an impact assessment.

B. Prepare a new purchase order.

C. Select a new vendor.

D. Create a risk register.

Buy Now
Questions 13

A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?

A. Scope creep

B. Collecting requirements

C. Decision-making

D. Project change

Buy Now
Exam Code: PK0-005
Exam Name: CompTIA Project+ (2026)
Last Update: Jun 12, 2026
Questions: 617
10%OFF Coupon Code: SAVE10

PDF (Q&A)

$49.99

VCE

$55.99

PDF + VCE

$65.99