Pass4itsure > CompTIA > CompTIA Project+ > PK0-004 > PK0-004 Online Practice Questions and Answers

PK0-004 Online Practice Questions and Answers

Questions 4

A program manager informs a project manager that a new, high-priority project has been approved and will need the current project's resources before the scheduled project close date. The project team meets and determines that the project should be fast-tracked.

Which of the following documents should the project team reference to fast-track the project? (Choose two.)

A. Scope management plan

B. Configuration management plan

C. Network diagram

D. Project schedule

E. Project plan

Buy Now
Questions 5

A company purchased a parachute supplier and is now sending parachutes to the research and development department. Which of the following has occurred?

A. Risk avoidance

B. Outsourcing

C. Business demerger

D. Business acquisition

Buy Now
Questions 6

A key stakeholder cannot identify within the resource management plan where the project manager has authority to assign resources. Which of the following should the project manager use to answer the question?

A. Project schedule

B. Project management plan

C. Project charter

D. Staffing matrix

Buy Now
Questions 7

A project team has just finished one phase of product development and is gathering requirements for the next phase. Which of the following methodologies is being applied?

A. Waterfall

B. PRINCE2

C. Agile

D. Top-down

Buy Now
Questions 8

A solid line is connecting a project team member to two people above the member on the organizational chart.

Which of the following types of organization does this indicate?

A. Functional

B. Merged

C. Split

D. Matrix

Buy Now
Questions 9

A concrete pad needs to be laid for a new house and requires three days to cure. The project manager notes that rain may be in the immediate forecast.

Which of the following would BEST avoid the risk of rain damage?

A. Place a tarp over the fresh concrete to protect it.

B. Refinish the concrete if it rains during that time.

C. Pour the concrete as quickly as possible to allow the most drying time.

D. Wait to pour the concrete until rain is not in the forecast.

Buy Now
Questions 10

A project stakeholder approaches the project manager and wishes to know how long the vendor will provide support for the application being developed for the project.

This information should be provided during the:

A. closure meeting.

B. kickoff meeting.

C. stand-up meeting.

D. team meeting.

Buy Now
Questions 11

A finance company hired a software consulting company to develop a new system. During the testing phase, the finance company's testing team found a major defect. The software consulting company states the software was constructed per the approved design.

Which of the following documents should be used to clarify the situation?

A. Letter of intent

B. Requirements document

C. Statement of work

D. Service-level agreement

Buy Now
Questions 12

A project sponsor would like the status of a key deliverable at the first project milestone.

Which of the following is a characteristic of a milestone?

A. Ongoing

B. Resource assigned

C. High cost

D. Zero duration

Buy Now
Questions 13

After accepting and assigning a positive risk, risk owners have a responsibility to:

A. maximize the probability.

B. update the risk register.

C. minimize the impact.

D. determine a mitigation strategy.

Buy Now
Exam Code: PK0-004
Exam Name: CompTIA Project +
Last Update: Sep 07, 2023
Questions: 727
10%OFF Coupon Code: SAVE10

PDF (Q&A)

$45.99

VCE

$49.99

PDF + VCE

$59.99