Pass4itsure > CompTIA > CompTIA Certifications > PK0-003 > PK0-003 Online Practice Questions and Answers

PK0-003 Online Practice Questions and Answers

Questions 4

Additional company employees have been assigned to the project. Which of the following will be affected?

A. The timeline may be positively affected at the expense of the project cost.

B. This change does not affect the triple constraint because the additional employees are already on the company payroll.

C. The quality of the product will improve but it will add more time to the project to train the new employees.

D. Total project cost will be reduced because the project can now be completed sooner.

Buy Now
Questions 5

Which of the following is included in the project charter?

A. Work assignments

B. Problem statement

C. Cost-benefit analysis

D. Feasibility assessments

Buy Now
Questions 6

A project stakeholder wants to make changes to a project after work on the project has already started. Which of the following should the project manager do FIRST?

A. Assign the request a tracking number and record in change request log

B. Recruit new project team members to expedite the change's completion date

C. Perform an analysis on the requested change submitted by the stakeholder

D. Submit stakeholder's change request to the change control board

Buy Now
Questions 7

The project manager of a project that involves a system-wide computer update receives a report that some computers cannot be updated. Which of the following is a BEST practice?

A. Contact the stakeholders in the project to determine the best course of action.

B. Complete a project management change form without notifying the sponsor.

C. Document the change to the project without informing the stakeholders.

D. Perform an impact analysis and contact the project sponsor.

Buy Now
Questions 8

The business stakeholder has been engaged late and has just had a chance to review the approved requirements. Consequently, it has been identified that there are a number of gaps in the requirements which are critical to the stakeholder's business unit. Which of the following actions should the project manager take?

A. Initiate change control

B. Follow communications plan

C. Manage project quality

D. Prepare a performance report

Buy Now
Questions 9

The final project report should contain which of the following?

A. Minutes of all the project meetings

B. Project design documentation

C. Detailed breakdown of the schedule

D. Summary of the project cost

Buy Now
Questions 10

Which of the following plans would MOST likely contain a probability and impact matrix?

A. Communication

B. Resource

C. Risk

D. Project

Buy Now
Questions 11

A project starts out as a small three month project. One month into the project, a stakeholder asks the team for additional functionality, which is estimated to take an additional three weeks. The project manager implements the functionality while waiting for approval. This is known as which of the following?

A. Change request

B. Risk

C. Resource constraint

D. Scope creep

Buy Now
Questions 12

Given the schedule estimates of Best Case = 2 days, Worst Case = 12 days, and Most Likely = 4 days, calculate PERT.

A. 4 days

B. 5 days

C. 6 days

D. 8 days

Buy Now
Questions 13

All of the following are characteristics of a project EXCEPT that it:

A. is managed by consensus.

B. is a temporary endeavor to create a unique product or service.

C. is limited by human and financial resources.

D. adheres to the triple constraint.

Buy Now
Exam Code: PK0-003
Exam Name: CompTIA Project+
Last Update: Jun 09, 2026
Questions: 320
10%OFF Coupon Code: SAVE10

PDF (Q&A)

$49.99

VCE

$55.99

PDF + VCE

$65.99