Pass4itsure > Microsoft > Microsoft Certifications > MB-335 > MB-335 Online Practice Questions and Answers

MB-335 Online Practice Questions and Answers

Questions 4

You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item. The item has the following Lean setup:

1.

The setup uses a Lean schedule group with a throughput ratio=2

2.

The process activity tied to production flow has the following runtime activity times: time=3 min, per quantity=1

3.

The work cell capacity has a model type of Throughput and an average throughput quantity of 60 per a capacity period of standard workday (8-hour day)

4.

The throughput is 10 per hour

You need to set up a Discrete operation to mirror the item's production flow activity.

What should you do?

A. Create a route with a runtime =1, a process quantity =6, and the operation's hours/time =1

B. Create a route with a runtime =1, a process quantity =10, and the operation's hours/time =1

C. Create a route with a runtime =6, a process quantity =1, and the operation's hours/time =1

D. Create a route with a runtime =10, a process quantity =6, and the operation's hours/time =1

Buy Now
Questions 5

A manufacturing company has a new speaker that is available with standard and premium carbon fiber options.

For the premium option, speakers are made to order. Customers can choose from seven product attributes at different prices.

You need to create and configure the product and pricing for the new speaker.

Solution: Create a dimension-based product master with variants and use the trade agreements to specify the different pricing.

Does the solution meet the goal?

A. Yes

B. No

Buy Now
Questions 6

A company has three jobs in a job queue. JobB and JobC start while JobA is in progress. The following table shows the estimated production time for each job.

The actual work hours and total bundle time are shown in the following table.

You need to calculate the allocated time for JobA by using a job allocation key. What is the total allocated time for JobA?

A. 1 hour

B. 2 hours

C. 4 hours

D. 6 hours

E. 8 hours

Buy Now
Questions 7

You need to configure the system to track the cost and delivery performance of VendorX. Which two actions should you perform? Each correct answer presents a complete solution.

A. Create a service product and set Stocked product = No.

B. Add an activity to the production route for deliveries.

C. Add an activity to the production flow for deliveries.

D. Create a service product and set Stocked product = Yes.

Buy Now
Questions 8

HOTSPOT

A company implements Dynamics 365 Supply Chain Management. You must use functionality in the system for group production runs to prevent downtime and excessive cleaning of the machines on the production line.

You need to set up the system.

Which behaviors should you expect? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

Hot Area:

Buy Now
Questions 9

HOTSPOT

A company makes engine parts used in the automotive industry.

They are in the process of retooling an existing manufacturing plant. They are looking to use Dynamics 365 Supply Chain Management to help support the Bill of Materials (BOM) product lifecycle for engineering version control.

You must translate existing production processes into the proper elements. You need to create BOM lifecycle states to translate existing production processes into the proper elements.

What type of BOM product lifecycle state should you create? To answer, select the appropriate BOM state in the answer area.

Hot Area:

Buy Now
Questions 10

HOTSPOT

You need to configure system attributes.

Which attribute types should you use? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

Hot Area:

Buy Now
Questions 11

HOTSPOT

You need to configure scheduling for each production area.

Which scheduling options should you use? To answer, select the appropriate option in the answer area.

NOTE: Each correct selection is worth one point.

Hot Area:

Buy Now
Questions 12

DRAG DROP

A manufacturer is implementing Dynamics 365 Supply Chain Management to create blends of oil and industrial lubricant.

The manufacturer requires detailed documentation for the production order process before manufacturing begins for the products. The shop floor must review, approve, and anticipate all production runs. Before production starts, the

manufacturer wants to ensure that the order can be completed by a certain timeframe based on capacity.

You need to define the production life cycle stages.

Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Select and Place:

Buy Now
Questions 13

DRAG DROP

You need to set up the system to calculate the overhead rates automatically for production.

Which four actions should you perform in sequence?

To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Select and Place:

Buy Now
Exam Code: MB-335
Exam Name: Microsoft Dynamics 365 Supply Chain Management Functional Consultant Expert
Last Update: May 24, 2026
Questions: 235
10%OFF Coupon Code: SAVE10

PDF (Q&A)

$49.99

VCE

$55.99

PDF + VCE

$65.99