Pass4itsure > CompTIA > CompTIA Certifications > JK0-017 > JK0-017 Online Practice Questions and Answers

JK0-017 Online Practice Questions and Answers

Questions 4

Which of the following risk response strategies involves shifting the negative impact of a threat, along with ownership of the response, to a third party?

A. Risk transfer

B. Risk avoidance

C. Risk sharing

D. Risk mitigation

Buy Now
Questions 5

The lessons-learned activity and formal acceptance documentation form part of which of the following process groups?

A. Closing

B. Planning

C. Executing

D. Monitoring/Controlling

Buy Now
Questions 6

The purpose of a WBS dictionary is to provide:

A. additional details for each component of the WBS, and for each component provide a brief definition of its statement of work, outputs, actual activities and pertinent milestones.

B. a detailed glossary of terms used in the WBS.

C. written authorization to sanction work on a particular work-package within the WBS, and define the methods for its implementation and the monitoring of its performance.

D. a hierarchical decomposition of the work to be undertaken to address the objectives and meet the requirements of the project at the lowest level.

Buy Now
Questions 7

Which of the following would measure a project's validity?

A. Risk analysis

B. Strategic alignment

C. Resource allocation

D. Gantt chart

Buy Now
Questions 8

Which of the following would be goals of an effective kick-off meeting? (Select Two).

A. To create the project charter

B. To create the statement of work (SOW)

C. To outline the communication plan

D. To set team member expectations

E. To determine the critical path of the project

Buy Now
Questions 9

In regards to proper change management procedures, which of the following would be the FINAL activity?

A. Coordinate with the appropriate stakeholders to determine course of action.

B. Document the change using the appropriate change control forms.

C. Perform impact analysis with project team members.

D. Update the project plan components based on the approved change request.

Buy Now
Questions 10

Which of the following would be included in a project scope document? (Select Three).

A. Project constraints

B. Gantt chart

C. Work Breakdown Structure (WBS)

D. Project roles and responsibilities

E. Key Performance Indicators (KPIs)

F. Detailed project objectives

Buy Now
Questions 11

The communication plan for a project is a subset of which of the following documents?

A. Project charter

B. Risk management plan

C. Project schedule

D. Project plan

Buy Now
Questions 12

A project manager is using a vendor with a fixed bid contract. The vendor would like to help out with other

parts of the project.

Which of the following should the project manager do NEXT?

A. Review the vendors SOW and determine if the additional work items can be included.

B. Allow the vendor to accept the additional work on a time and material (TandM) basis.

C. Allow the vendor to accept the additional work, but honor the fixed bid price.

D. Explain to the vendor that the work is already assigned to the vendor with the lowest cost.

Buy Now
Questions 13

To ensure the quality of implemented project change requests, which of the following will need to occur? (Select Two).

A. The project team is not notified of the approved change.

B. Change is tracked and is either accepted or rejected by the change control board.

C. Change is logged and updated in the change log document.

D. Once a change is forwarded to the change control board, it will be removed from the change log.

E. Once the change is submitted to the change control board, it will be approved and placed into production.

Buy Now
Exam Code: JK0-017
Exam Name: CompTIA E2C Project+
Last Update: May 27, 2026
Questions: 402
10%OFF Coupon Code: SAVE10

PDF (Q&A)

$49.99

VCE

$55.99

PDF + VCE

$65.99