What are key goals of the burndown chart? Note: There are 2 correct ans-wers to this que-stion.
A. Determination of the overall availability of the team for the future sprints
B. Assignment of backlog items to future sprint up to completion of the release
C. Visualization of the size of the backlog consumed so far
D. Determination of the planned go-live date based on current velocity
In SAP Activate, what tool is used in the agile delivery approach during the Realize phase to make forecasts based on actual data?
A. Scrum board
B. Product backlog
C. Burndown chart
D. Release plan
Which estimation technique can be used in an Agile delivery approach to size the User Stories during sprint planning?
A. Leveraging effort estimates for similar User Stories from another Scrum team
B. Detailed bottom-up estimates that break each User Story into shorter tasks
C. Relative estimates in Ideal Person Days that reflect the best estimates provided by the project team
D. Detailed top-down estimates by the Scrum Master in story points or Ideal Person Days
What is the purpose of the scrum board? Note: There are 2 correct ans-wers to this que-stion.
A. To represent the scrum team setup
B. To visualize scrum team progress
C. To represent the work
D. To manage the scrum resources load
You are defining the testing strategy for your project.
What would you include in a scope of Integration Test? Note: There are 2 correct ans-wers to this que-stion.
A. Interfaces with other applications
B. Connectivity between database and application servers
C. Quality of data for migration
D. Functionality of end-to-end business processes
Which of the following is part of the Explore phase for new implementations? Note: There are 2 correct ans-wers to this que-stion.
A. Data load preparation
B. Fit-to-standard
C. Cutover plan
D. Customer self-enablement
Which of the following belong to the Application Design and Configuration workstream in the Explore phase? Note: There are 2 correct ans-wers to this que-stion.
A. Configuration definition
B. Change Impact Analysis
C. Integration prerequisites confirmation
D. Fit-to-standard workshop
When do you perform Quality Gate (Q-Gate) during a project? Note: There are 2 correct ans-wers to this que-stion.
A. At the end of Realize phase
B. At the end of Prepare phase
C. At the end of Discover phase
D. At the end of Run phase
In which phase of SAP Activate does the SAP Project Manager set up project governance?
A. Explore
B. Prepare
C. Realize
D. Discover
Working in an Agile approach, what should your planning look like at the beginning of the Realize phase?
A. Scope and duration of testing is finalized.
B. Durations of all sprints for the full release defined based on planned complexity.
C. User Stories are in Ready state for only the first 2 to 3 sprints.
D. Project scope and planning are completed and final.