An intentional activity to modify a nonconforming product or product component is called:
A. defect repair
B. work repair
C. corrective action
D. preventive action
When would resource leveling be applied to a schedule model?
A. Before constraints have been identified
B. Before it has been analyzed by the critical path method
C. After it has been analyzed by the critical path method
D. After critical activities have been removed from the critical path
Which type of analysis is used to examine project results through time to determine if performance is improving or deteriorating?
A. Control chart
B. Earned value
C. Variance
D. Trend
Which of the following is an output of Direct and Manage Project Execution?
A. Project management plan
B. Change request status updates
C. Organizational process assets updates
D. Work performance information
Managing procurement relationships and monitoring contract performance are part of which process?
A. Conduct Procurements
B. Plan Procurements
C. Administer Procurements
D. Close Procurements
What are the identified risks for doing excessive decomposition in a WBS?
A. Insufficient project funding and disqualification of sellers
B. Insufficient project funding and ineffective use of resources
C. Disqualification of sellers and non-productive management efforts
D. Non-productive management effort and inefficient use of resources
Which of the following is an output of Define Scope?
A. Project scope statement
B. Project charter
C. Project plan
D. Project schedule
The process of developing a detailed description of the project and product is known as:
A. Create WBS.
B. Verify Scope.
C. Collect Requirements.
D. Define Scope.
Which is a list of organizational systems that may have an impact on a project?
A. Internal policies, company procedures, and organizational resources
B. Company culture, purchasing system, and project management information system
C. Organizational structure, governance framework, and management elements
D. Organizational process assets, enterprise environmental factors, and corporate knowledge
What process group establishes project scope: refines objectives, and defines the actions necessary to attain project objectives'?
A. Executing
B. Planning
C. Initiating
D. Monitoring and Controlling