Questions 4

Revenues and Payment

A customer use cross-company-code project with a top billing element and additional billing element underneath (por debajo) for each company code. Although the internal .. correctly the result analysis summarizes all values to the highest billing element. How can they split the results to the different company codes?

A. Settle the WBS element to the highest billing element before you do the result analysis.

B. Split the project intdifferent project according to each company code.

C. Change the project structure so that it correspond better to the company's organization structure.

D. Adjust the customizing of the valuation method in the expert mode of the periodic results analysis accordingly.

Buy Now
Questions 5

For which objects can billing plans be created? Note: There are 2 correct answers to this question

A. WBS elements

B. Project definition

C. Sales order items

D. Milestones

Buy Now
Questions 6

Which objects can be used to specify settlement rules? Note: There are 2 correct answers to this question?

A. Standard WBS elements

B. Network header for activity-account-assigned networks

C. WBS elements

D. Network activity for activity-account-assigned networks

Buy Now
Questions 7

Materials

Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set of dates that can be scheduled.

Which set of dates can be used for scheduled for network?

Note : there are 2 correct answer for this question.

A. Planned dates

B. Fundamental dates

C. Basic dates

D. Baseline dates

E. Forecast dates

Buy Now
Questions 8

You have saved a network and activates with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out" What could be the reason for this error message?

A. Missing budget for material components

B. Missing reservations for material components

C. Missing material availability

D. Missing authorizations to release material components

Buy Now
Questions 9

When you create a service activity in your network, what data can be entered? Note: There are 3 correct answers to this question.

A. Service specification

B. Overall limit (maximum value of all unplanned services)

C. Service purchase order number

D. Material master within service specification

E. Vendor

Buy Now
Questions 10

Your costumer Project/planning Board to create/update Gant charts. Which the following are characteristics of the Project Planning Board.

Note : there are 3 correct answers for this question.

A. Display of production orders assigned to WBS element.

B. Display of plant maintenance orders for activities.

C. Display of project cost plan.

D. Display of project-relevant purchase order.

E. Using specific color management for Gantt Chart.

Buy Now
Questions 11

Resources

How can you define external task in your project.

Note : there are 2 correct answers for this question.

A. Assign a purchase order for external processing to the project definition.

B. Create an external activity in a network.

C. Create a service milestone.

D. Create a service activity in a network.

Buy Now
Questions 12

To which object can you assign a factory calendar?

A. Material component

B. Network header

C. Relationship

D. Milestone

Buy Now
Questions 13

Cost and budget

A service Company use project management and they complain that the system does not prevent their project manager from exceeding their budget.

What action do you have tsolve the problem?

A. Activate availability control For projects in the control area. Enter the plan data for each WBS element.

B. Activate availability control for the important WBS element. Define the tolerance limit on each WBS element.

C. Activate availability control in the assign budget profile. Defined the tolerance limit in the customizing.

D. Activate commitment management in the project definition. Enter the budget in the master data of the top WBS element.

Buy Now
Exam Code: C_TS412_2021
Exam Name: SAP Certified Associate - SAP S/4HANA Project Systems
Last Update: May 26, 2026
Questions: 110
10%OFF Coupon Code: SAVE10

PDF (Q&A)

$49.99

VCE

$55.99

PDF + VCE

$65.99