How do you evaluate and display details of orders and networks that create capacityrequirements at the
work centers?
Please choose the correct answer.
Response:
A. Standard overview
B. Capacity detail list
C. Variable overview
D. Tabular overview
Which type of network does not allow you to assign materials directly, but only indirectly using a bill of
materials?
Please choose the correct answer.
A. Operative network
B. Internal network
C. Standard network
D. Task network
Which technique is one of the ways to measure the earned value where each milestone corresponds to a percentage of work completed in an activity or a WBS element in progress analysis? Please choose the correct answer.
A. Project technique
B. Trend technique
C. Milestone technique
D. Period indicator technique
Which of the following related to an activity stipulates the activity type and determines how an activity is handled during calculation, scheduling and capacity planning? Please choose the correct answer.
A. Customizing key
B. Control key
C. Scheduling key
D. Confirmation key
If the available user-definable fields do not satisfy your requirement, you have an option to develop
additional fields for which of the following.
There are 2 correct answers to this question.
A. WBS elements
B. Activities
C. Project definition
D. Tasks
Which indicator do you use to define the characteristics of a WBS element and to specify tasks that are performed by the WBS element when the project is executed? Please choose the correct answer.
A. Cost indicators
B. Billing indicators
C. Operative indicators
D. Project cost indicators
Most of the reports in the SAP Project System can be refreshed without exiting or closing the report. Which
report must be restarted to update the displayed data? Please choose the correct the answer.
Response:
A. Hierarchical Reports
B. Individual Overviews
C. Reports by Cost Element
D. Structure Overview
Which of the following helps you to adjust cost planning to changing circumstances during the execution
phase of the project?
Please choose the correct answer.
Response:
A. Progress analysis
B. Cost forecasts
C. Overhead costs
D. Interest forecast
How does a project manager plan resources in cProjects and define responsibilities for different objects?
There are 2 correct answers to this question.
Response:
A. Users
B. Alerts
C. Roles
D. Business partners
Which of the following items can be included in the planned costs for an activity besides the cost of the
activity? There are 3 correct answers to this question.
Response:
A. Activity elements
B. Overheads determined through overhead costing sheet
C. Process costs determined through a process template
D. Material management cost