Which one is a product risk associated with the air quality management system?

A. The system required to monitor oxygen levels may be more expensive than those required to monitor air temperatures.

B. SubsInc may need to recruit extra developers and testers to deliver the project on time.

C. Oxygen levels may reach dangerously low levels.

D. Extreme temperatures may lead to heat exhaustion of personnel.

Buy Now
Questions 5

Which of the following is an accurate depiction of the hierarchy of test management documentation (where the highest comes first)?

A. Test policy-Test strategy-Project test plan-System test plan

B. Test strategy-Test policy-Project test plan-System test plan

C. Test policy-Project test plan-Test strategy-System test plan

D. Project test plan-Test strategy-System test plan-Test policy

Buy Now
Questions 6

Which stage of the Fundamental Test Process will be most affected by the use of user-stories as defined above?

A. Creating a schedule of activities as part of test planning.

B. Creating test cases as part of test design.

C. Creating the test environment as part of test execution.

D. Assessing requirements coverage at the end of each Sprint.

Buy Now
Questions 7

Which of the following review types would be recommended at the start of each Sprint, for the reason given?

A. An inspection, to find errors in the user-stories.

B. A management review, to check that the user-stories will accurately reflect the rules for accessibility.

C. A walkthrough of the set of user-stories, to ensure that the developers and testers understand what is to be built.

D. A technical review of the test plan, to ensure that the developers are aware that they must produce

good quality code.

Buy Now
Questions 8

Which of the following would be applicable as part of a test policy for testing these types of systems?

a.

Systems must be tested for compliance to industry standard routing protocols.

b.

Testing for the latest upgrade will require testing of increased network traffic of 100%.

c.

Testing for the fix will require the use of dynamic analysis tools.

d.

Releases will not be made if systems have any high priority defects outstanding.

A.

a and b.

B.

a and d.

C.

b and c.

D.

b and d.

Buy Now
Questions 9

Which of the following reviews would you recommend to address this issue?

A. A walkthrough of the requirement specification, to check for errors.

B. A management review of defects logged and cleared to see if defects are being addressed correctly.

C. A technical review of the industry standard routing protocols to see if they have inaccuracies in them.

D. An inspection of the code for this part of the functionality to try to localise the defective parts of the code.

Buy Now
Questions 10

You need to test that the rules have been correctly set up in the configuration table, according to the specification. Which one of the following test design techniques would be most suitable for this?

A. Data flow testing.

B. Statement testing.

C. Decision table testing.

D. Boundary value analysis.

Buy Now
Questions 11

When a software defect in a system has been found and fixed, which of the following activities should be undertaken next?

a.

Debugging.

b.

Confirmation testing.

c.

Regression testing.

d.

System testing.

e.

Static testing.

A.

a and b.

B.

b and c.

C.

c and d.

D.

c and e.

Buy Now
Questions 12

Which of the following test design techniques could be used to do this?

a.

Statement testing.

b.

Path testing.

c.

State transition testing.

d.

Exploratory testing.

A.

a and c.

B.

b and c.

C.

c and d.

D.

a and d.

Buy Now
Questions 13

Which of the following provides the best example of a product risk leading to a project risk?

A. The signalling systems may have more defects than anticipated, leading to the need for more retesting to be carried out.

B. There may be unexpected lags on the network traffic communication, causing drivers to slow the trains down unnecessarily.

C. The new development staff may require training for this type of system, which, if not carried out, may lead to an increase in the number of defects introduced.

D. The budget may need to be increased significantly during the project, otherwise there may be delays in the delivery of the system.

Buy Now
Exam Code: BH0-007
Exam Name: ISEB Intermediate Certificate in Software Testing
Last Update: Mar 20, 2024
Questions: 25
10%OFF Coupon Code: SAVE10