The Perform Quality Assurance process occurs in which Process Group?
A. Executing
B. Monitoring and Controlling
C. Initiating
D. Planning
Which process involves subdividing project deliverables and project work into smaller, more manageable portions?
A. Develop Schedule
B. Create VVBS
C. Estimate Activity Resources
D. Define Scope
Identify Risks is part of which Process Group?
A. Planning
B. Executing
C. Closing
D. Initiating
The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:
A. start-to-start (SS)
B. start-to-finish (SF)
C. finish-to-start (FS)
D. finish-to-finish (FF)
If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?
A. One
B. Five
C. Six
D. Seven
Which technique helps to determine the risks that have the most potential impact on a project?
A. Cost risk simulation analysis
B. Expected monetary value analysis
C. Modeling and simulation
D. Sensitivity analysis
An input to the Perform Quantitative Risk Analysis process is the:
A. quality management plan.
B. project management plan.
C. communications management plan.
D. schedule management plan.
Which of the following types of a dependency determination is used to define the sequence of activities?
A. Legal
B. Discretionary
C. Internal
D. Resource
A tool and technique used during the Define Scope process is:
A. facilitated workshops.
B. observations.
C. questionnaires and surveys.
D. group creativity techniques.
The correct equation for schedule variance (SV) is earned value:
A. minus planned value [EV - PV].
B. minus actual cost [EV - AC].
C. divided by planned value [EV/PV].
D. divided by actual cost [EV/AC].