Questions 4

The Perform Quality Assurance process occurs in which Process Group?

A. Executing

B. Monitoring and Controlling

C. Initiating

D. Planning

Buy Now
Questions 5

Which process involves subdividing project deliverables and project work into smaller, more manageable portions?

A. Develop Schedule

B. Create VVBS

C. Estimate Activity Resources

D. Define Scope

Buy Now
Questions 6

Identify Risks is part of which Process Group?

A. Planning

B. Executing

C. Closing

D. Initiating

Buy Now
Questions 7

The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:

A. start-to-start (SS)

B. start-to-finish (SF)

C. finish-to-start (FS)

D. finish-to-finish (FF)

Buy Now
Questions 8

If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?

A. One

B. Five

C. Six

D. Seven

Buy Now
Questions 9

Which technique helps to determine the risks that have the most potential impact on a project?

A. Cost risk simulation analysis

B. Expected monetary value analysis

C. Modeling and simulation

D. Sensitivity analysis

Buy Now
Questions 10

An input to the Perform Quantitative Risk Analysis process is the:

A. quality management plan.

B. project management plan.

C. communications management plan.

D. schedule management plan.

Buy Now
Questions 11

Which of the following types of a dependency determination is used to define the sequence of activities?

A. Legal

B. Discretionary

C. Internal

D. Resource

Buy Now
Questions 12

A tool and technique used during the Define Scope process is:

A. facilitated workshops.

B. observations.

C. questionnaires and surveys.

D. group creativity techniques.

Buy Now
Questions 13

The correct equation for schedule variance (SV) is earned value:

A. minus planned value [EV - PV].

B. minus actual cost [EV - AC].

C. divided by planned value [EV/PV].

D. divided by actual cost [EV/AC].

Buy Now
Exam Code: APM-001
Exam Name: Certified Associate in Project Management (APM)
Last Update: May 28, 2026
Questions: 704
10%OFF Coupon Code: SAVE10

PDF (Q&A)

$49.99

VCE

$55.99

PDF + VCE

$65.99