Identify the missing words in the following sentence.
Principles 1 -Focus on the Business Need suggests that every decision taken during a project should be [?] -to deliver what the business needs to be delivered.
A. The responsibility of the Business Sponsor
B. Share between all of the project roles
C. Viewed in light of the overriding project goal
D. Made collaboratively
Identify the missing word in the following sentence.
The Business Sponsor is known as the project [?] because they are committed to the solution and the delivery approach.
A. Governor
B. Champion
C. Visionary
D. director
Which plain defined by DSDM, has a planning horizon that includes the end of a project?
A. Timebox
B. Detailed
C. Delivery
D. High-Level
Which competence is NOT required within the Solution Development team?
A. All members to be multi-skilled experts
B. Business knowledge
C. Technical expertise
D. Willingness to work with other
What does DSDM refer to the Minimum Usable Subset?
A. The Must, Should and Could have requirements
B. All requirements in the functional specification
C. The Must Have requirements
D. Those requirements that have passed user acceptance testing
Which of the following is a stated benefit of using DSDM?
1.
The business is better able to direct development
2.
Designs are based on predicted
3.
The risk of building the wrong solution Is reduced
4.
Deployment is more likely to go smoothly
A. 1, 2, 3
B. 2, 3, 4
C. 1, 3, 4
D. 1, 2, 4
Which of the following are recognized DSDM styles of Timebox?
1.
Unstructured
2.
Consolidated
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 is true
How is contingency typically managed in a DSDM project?
A. Not needed in a DSDM project.
B. Allowed adding a percentage to the high-level estimates.
C. Managed by varying the features to be delivered.
D. Managed by varying time and cost
Which statement about change is correct for DSDM?
A. Change is a symptom of an inability to define requirements properly
B. Avoid change whenever possible
C. Change is inevitable and males estimating very difficult
D. Project operate with a changing world
What is the MoSCoW technical used for?
A. Understanding and managing priorities.
B. Ensuring a team-based approach through visual and verbal communication and collaboration.
C. Creating a visual representation of a problem or a solution.
D. As an opportunity to share information across the team and to do any day.to.day re- planning and reorganizing as necessary when issues occur.