Pass4itsure > CompTIA > CompTIA Project+ > PK0-003 > PK0-003 Online Practice Questions and Answers

PK0-003 Online Practice Questions and Answers

Questions 4

The project team is geographically split between two time zones. Which of the following should be performed by the project manager?

A. Escalate to the project sponsor with a preference to replace the remote members with local members.

B. Set up meeting times that are not necessarily a perfect fit, but are fair to both locations.

C. Schedule two separate meetings at the desired local time for the participants.

D. Convert traditional meetings into email updates and catch up on an exceptions basis.

Buy Now
Questions 5

Which of the following is a common cause of conflict when dealing with the human resource aspect of project management?

A. Similar personal values among team members

B. Different roles among team members

C. Similar project goals among team members

D. Different work styles among team members

Buy Now
Questions 6

Which of the following is a component of a risk management plan?

A. RAM

B. RBS

C. COQ

D. KPI

Buy Now
Questions 7

A project manager is involved with minimizing unauthorized changes to the project. Which of the following will BEST assist with these changes?

A. Risk register

B. Quality management metrics

C. Scope statement

D. Budget scope

Buy Now
Questions 8

A project has been going on for three weeks, and the project manager notices that Resource A is beginning to fall behind schedule. The project manager should FIRST schedule a meeting with:

A. The project stakeholders to communicate the delay.

B. Resource A to confirm estimates.

C. The other team members to make up the schedule slippage.

D. The manager of Resource A for corrective action.

Buy Now
Questions 9

A key stakeholder has requested a change to the delivery frequency of the risk register. Which of the following documents should be updated?

A. Communications Plan

B. Risk Register

C. Work Breakdown Structure

D. Change Log

Buy Now
Questions 10

Which of the following is the purpose of identifying stakeholders?

A. To identify who is not affected by a project

B. To identify who is not required for the project

C. To identify who will be affected by a project

D. To identify who provides resources

Buy Now
Questions 11

Which of the following would aid in the creation of a communication distribution plan?

A. Risk register

B. Stakeholder register

C. Issue log

D. Change control log

Buy Now
Questions 12

Which of the following would be found in a transition plan? (Select TWO).

A. Key milestones

B. Project acceptance criteria

C. Training requirements

D. Tollgate approvals

E. Extended support

Buy Now
Questions 13

During which of the following process groups is the project charter developed?

A. Pre-project setup

B. Project execution

C. Project planning

D. Project control

Buy Now
Exam Code: PK0-003
Exam Name: CompTIA Project+ (2009)
Last Update: Apr 27, 2024
Questions: 320
10%OFF Coupon Code: SAVE10

PDF (Q&A)

$45.99

VCE

$49.99

PDF + VCE

$59.99