Which Activity Duration Estimating technique incorporates additional timing for contingency purposes?
A. Analogous Estimating
B. Expert Judgment
C. Optimistic Estimates
D. Reserve Analysis
What are the formal and informal policies, procedures, and guidelines that could impact how the project's scope is managed?
A. Organizational process assets
B. Enterprise environmental factors
C. Project management processes
D. Project scope management plan
What causes replanning of the project scope?
A. Requested changes
B. Project scope statement changes
C. Variance analysis
D. Approved change requests
What should be covered in an implementation when the change is approved?
A. Functional requirement
B. Status report
C. Customer need
D. Defect repair
You are project manager of a project. During the process of selecting the sellers, you reject one vendor because it doesn't have the manufacturing capability. This is an example of which selection tool?
A. Weighting system
B. Screening system
C. Seller rating system
D. Expert judgment
A project plan is:
A. A formal, approved document used to guide both project execution and project control.
B. A document issued by senior management that provides the project manager with the authority to apply organizational resources to project activities.
C. A narrative description of products or services to be supplie
D. A document describing the organizational breakdown structure of the company.
To calculate the late start and late finish dates for a set of tasks , you must do :
A. An analysis of the critical path
B. A forwards pass
C. A backwards pass
D. a and g
Which is not included in Performance improvements :
A. Improvements in amount of overtime worked
B. Improvements in individual skills
C. Improvements in team behaviours
D. Improvements in team capabilities
Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the PERT weighted average?
A. 6
B. 4
C. 6.3
D. 6.1
A scope management plan In which of the following scope management processes is the scope management plan prepared?
A. Initiation
B. Collect Requirements
C. Define Scope
D. Verify Scope